Interior work

Progress is mostly on the interior over the last few weeks. The plumbers and electricians have been in, and the pex tubing for radiant floor heating has been laid. They sealed up parts with expanding soy-based foam insulation. The doors have been on back-order, so they haven't quite beenable to close up the building and finish the last bits of siding. After that, more electric work, the drywall (next week?), and painting. But the kitchen cabinets will take a while.